Here is The CONSTRUCTION MANAGEMNT Multiple choice Question please Don't forgot to SHARE and LIKE our page
1. Which one of the following represents an
activity
A. excavation for foundation
B. curing of concrete
C. setting of question paper
D. preparation of breakfast
E. all the above.
Answer: Option E
2. Pick up the incorrect statement from the
following:
A. An activity of a project is denoted by
an arrow on the net work
B. The tail of the arrow indicates the start
of the activity
C. The head of the arrow indicates the
end of the activity
D. The arrows are drawn to scale from
left to right
E. Each activity consumes a given time.
Answer: Option D
3. The technique for establishing and maintaining
priorities among the various jobs of a project,
is known
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling.
Answer: Option B
4. Mile Stone charts were invented in the year of
A. 1910
B. 1920
C. 1930
D. 1940
E. 1950
Answer: Option D
5. Frederick W. Taylor introduced a system of
working known as
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation.
Answer: Option C
6. Pick up the PERT event from the following:
A. Digging of foundation started
B. Digging of foundation completed
C. Laying of concrete started
D. Laying of concrete completed
E. All the above.
Answer: Option E
7. If D is the duration, ES and EF are the earliest
start and finish, LS and LF are latest start and
latest finish time, then the following relation
holds good
A. EF = ES + D
B. LS = LF - D
C. LF = LS + D
D. D = EF - ES
E. all the above.
Answer: Option E
8. Final technical authority of a project lies with
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer.
Answer: Option D
9. The performance of a specific task in CPM, is
known
A. Dummy
B. Event
C. Activity
D. Contract.
Answer: Option C
10. Pick up the correct statement from the
following:
A. The float may be positive, zero or
negative
B.
If the float is positive and the activity
is delayed by a period equal to its
total float, the completion of project is
not delayed
C.
If the float of an activity is negative,
delay in its performance is bound to
delay the completion of project
D.
If the float of an activity is zero, the
activity is critical and any delay in its
performance will delay the whole
project
E. All the above.
Answer: Option E
11. A Milestone chart
A. shows the interdependencies of
various jobs
B. depicts the delay of jobs, if any
C. points outgoing ahead of schedule of
jobs, if any
D. none of these.
Answer: Option D
12. Completion of an activity on CPM network
diagram, is generally known
A. Event
B. Node
C. Connector
D. All the above.
Answer: Option D
13. A dummy activity
A. is artificially introduced
B. is represented by a dotted line
C. does not consume time
D. all the above.
Answer: Option D
14. Military organisation is known as
A. line organisation
B. line and staff organisation
C. functional organisation
D. none of these.
Answer: Option A
15. Pick up the incorrect statement from the
following:
A. The activity is the time consuming part
of a project
B. The beginning and end of a job, are
called events
C. The activity which consumes maximum
time, is called a node
D. Logically and sequentially connected
activities and events form a network
E. None of these.
Answer: Option C
16. Various activities of a project, are shown on
bar charts by
A. vertical lines
B. horizontal lines
C. dots
D. crosses.
Answer: Option B
17. Time and progress chart of a construction, is
also known as
A. Bar chart
B. Gantt chart
C. Modified Mile stone chart
D. Critical path method chart
E. All the above.
Answer: Option E
18. Critical Path Net Work helps an engineer
A. to concentrate his attention on critical
activities
B.
to divert the resources from non-
critical advanced activities to critical
activities
C.
to be cautious for avoiding any delay
in the critical activities to avoid delay
of the whole project
D. all the above.
Answer: Option D
19. The time by which activity completion time
can be delayed without affecting the start of
succeeding activities, is known as
A. duration
B. total flat
C. free float
D. interfering float.
Answer: Option C
20. The artificial activity which indicates that an
activity following it, cannot be started unless
the preceding activity is complete, is known
as
A. event
B. free float
C. dummy
D. constant
Answer: Option C
21. Henry Gantt developed Bar charts for planning
and scheduling of projects in
A. 1880
B. 1900
C. 1920
D. 1940
E. 1950
Answer: Option B
22. The most popular type of organisation used
for Civil Engineering Constructions, is
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation.
Answer: Option A
22. The difference between the time avail-to do a
job and the time required to do the job, is
known as
A. event
B. float
C. duration
D. constraint.
Answer: Option B
23. The object of technical planning, is
A. preparation of specifications
B. preparation of estimates
C. initiating the procurement action of
resources
D. taking remedial action for likely
bottleneck in the ex*****on
E. all the above.
Answer: Option E
24. The salient feature of functional organisation is
A. strict adherence to specifications
B. separation of planning and design part
C. each individual maintains functional
efficiency
D. work is properly planned and
distributed
E. all the above.
Answer: Option E
25. Critical path method
A. is an improvement upon bar chart
method
B. provides a realistic approach to daily
problems
C. avoids delays which are very common
in bar charts
D.
was invented by Morgan R. Walker of
Dupot and James E. Kalley or
Re*****on U.S.A. in 1957
E. All the above.
Answer: Option E
26. CPM is
A. synthesising in concepts
B. is built of activities oriented
programme
C. is based on time estimate
D. is used for repetitive works
E. all the above.
Answer: Option E
27. Critical path lies along the activities having
total float
A. positive
B. negative
C. zero
D. same.
Answer: Option C
28. Construction team means
A. an engineer
B. an architect
C. an owner
D. a contractor
E. all the above.
Answer: Option E
29. Pick up the correct network for the activities
of pouring concrete, er****on of form work,
removal of form work and curing of concrete
from the following:
A.
1. Pouring of Concrete
2. Er****on of form work
3. Curing of concrete
4. Removal of form work
B.
1. Er****on of form work
2. Pouring of concrete
3. Curing of concrete
4. Removal of form work
C.
1. Removal of form work
2. Er****on of form work
3. Pouring of concrete
4. Curing of concrete
D.
1. Pouring of concrete
2. Curing of concrete
3. Er****on of form work
4. Removal of form work
Answer: Option B
30 . A construction schedule is prepared after
collecting
A. number of operations
B. output of labour
C. output of machinery
D. quantity of various items
E. all the above.
Answer: Option E
31. Site order book is used for recording
A. instructions by the executive engineers
B. construction measurements
C. issue of store equipments
D. names of the casual labour.
Answer: Option A
32. The main principle of an organisation, is
A. unity of command
B. cohegency
C. effective control at all levels
D. delegation of authority
E. all the above.
Answer: Option E
33. The estimated time required to perform an
activity, is known as
A. event
B. dummy
C. duration
D. float.
Answer: Option C
34. A CPM family includes
A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
D. CPS (Critical Path Scheduling)
E. All the above.
Answer: Option E
35. The time which results in the leasi, possible
construction cost of an activity, is known
A. normal time
B. slow time
C. crash time
D. standard time.
Answer: Option B
36. If the total float and duration of an activity are
5 and 10 days respectively, the particular
activity can be
A. started 5 days later
B. completed 5 days later
C. performed at slower rate in 15 days
D. all the above.
Answer: Option D
37. Works costing less than 20,000 Birr. are
treated as
A. projects
B. major projects
C. minor projects
D. all the above.
Answer: Option C
38. A critical ratio scheduling
A.
establishes the relative priorities
among various activities on a common
basis
B. determines the status of each activity
C. adjusts automatically changes in
activity progress
D. is a dynamic system
E. none of these.
Answer: Option E
39. Bar charts are suitable for
A. minor works
B. major works
C. large projects
D. all the Above.
Answer: Option A
40. The first method invented for planning
projects, was
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme Evaluation and Review
Technique (PERT)
Answer: Option A
41. If TL is the latest allowable event occurrence
time, total activity slack(s), is equal to
A. LST-EST
B. LFT-EFT
C. TL-EFT
D. all the above.
Answer: Option D
42. The Overall in-charge of an organisation at the
site responsible for the ex*****on of the
works, is
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Sub overseer
E. Assistant Engineer.
Answer: Option B
43. Modular co-ordination of construction means
proper
A. planning
B. designing
C. ex*****on
D. all the above.
Answer: Option D
44. Pick up the correct statement from the
following:
A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C.
CPM does not make any allowance for
the uncertainties in the duration of
time
D. In CPM, the time is related to cost
E. All the above.
Answer: Option E
45. If t is the duration of an activity, t1 is the
latest finish possible moment of its preceding
activity and t 2 is the earliest start possible
moment, the independent float of the activity
is
A. (t 1 - t 2 ) - t
B. t - (t1 - t2)
C. (t 1 + t2 ) - t
D. t + ( t1 - t2)
Answer: Option A
46. Pick up the correct statement from the
following:
A. Earliest expected time is denoted by
TE
B. Latest occurrence time is denoted by
TL
C. Contractual obligation time is denoted
by Ts
D. Latest occurrence time is taken as
contractual obligation time
E. All the above.
Answer: Option E
47. For the supply of materials for concrete, form
work reinforcing and placing of concrete,
removal of form work and curing of concrete,
number of bar(s) required on bar chart, is
A. 1
B. 2
C. 3
D. 4
Answer: Option A
48. For the ex*****on of a project, a contractor is
A. a person
B. a firm
C. an agency
D. all the above.
Answer: Option D
49. Railway projects are treated as
A. light construction
B. heavy construction
C. industrial construction
D. none of these.
Answer: Option B
50. The critical activity has
A. maximum float
B. minimum float
C. zero float
D. none of these.
Answer: Option C
51. Pick up the correct statement from the
following:
A.
The difference of latest occurence time
and earliest expected time, is called
slack
B.
The activities connecting the events
having zero slack, lie on the critical
path
C. The critical path consumes the
maximum time
D. All the above.
Answer: Option D
52. Pre-tender stage requires
A. acquisition of land
B. selection of site
C. fmalisation of alignment of work
D. fmalisation of designs and preparation
of estimate
E. all the above.
Answer: Option E